The contracts of the Syrian regime government have been distributed between Russia and Iran, at a time when the first controlled the dams by virtue of the old experience and contracts with the Soviet Union, while the second entered the electricity contracts line including conversion, generation and the development process. What cannot be confirmed, however, is whether this distribution comes in the context of rivalry or sharing.
Enab Baladi has monitored Iranian and Russian projects and contracts signed with the Syrian government in the electricity sector, and has discussed the distribution of those projects between the two powers involved in the Syrian affairs.
The electrical energy sources in Syria are divided into renewable energy, under which hydroelectric stations are included, and the largest of which is the Tabqa Dam Station in the city of al-Thawrah in northeastern Syria, and Tishreen Station in the Abu Qilqil region in Aleppo Governorate in northern Syria. This is in addition to thermal stations that work with either gas or fuel, and the largest of which are the Aleppo station, which produces 1065 MW, and Jandar Station in Homs Governorate, which is the largest station in terms of production, at 1100 MWh.
Several stations were damaged during the war in Syria, but there are no exact figures about the damage in the electricity sector. The latest statistics for the losses were declared by the current Prime Minister and former Electricity Minister, Imad Khamis.
According to what Khamis said, in a hearing hearing session in the People’s Assembly, in February of 2016, the losses of the sector amounted to 1,500 billion Syrian Pounds, according to the prices of the electricity system’s materials and equipment at the time, since 2011 until the date of the statement.
Khamis said that five of the 13 major transfer stations, each with a value of 20 million euros, were attacked by what he described as “terrorist groups”.
Iran’s electricity power contracts in Syria
Iran entered the electricity production line in Syria, and signed diverse contracts including the development of the system and the establishment of generation and transfer stations distributed in several governorates, including Homs, Latakia, and Aleppo, in addition to a general agreement covering the development of the electricity sector and its equipment.
Since September, Iran has signed four contracts with the government of the Syrian regime, the first of which is the Homs Station Agreement, on September 5, when the Syrian International Educational Technology Systems signed with the Iranian Novin Energy Company, which is specialized in the generation of electric energy with renewable energy, a cooperation agreement to generate electric energy in the areas located between Homs and Hassia, with an initial production capacity of 5 megawatts, without clarifying the maximum production capacity of the plant, as reported by the official Syrian News Agency (SANA).
The second agreement included the Iranian private sector’s handing over of a 540-megawatt power station in Latakia, according to a statement made by the Iranian Energy Minister, Reza Ardakanian, on the sidelines of the Iranian Council of Ministers meeting, to the Iranian agency Tasnim on September 25, adding that exporting Iranian technical and engineering services is carried out at the regional level, especially in the field of water and electricity.
According to the Iranian minister, the transfer of the power plant came within the framework of a joint investment project, considering that the participation with foreign investors in rebuilding the electricity sector in Syria is important for Iran.
In the beginning of November, Syrian Electricity Minister Muhammad Zuhair Kharboutli, and his Iranian counterpart, Reza Ardakanian, signed an agreement including the electricity system and the development of electricity equipment in Syria. The agreement also includes the work on rebuilding the electricity system in Syria, the localization of the electricity equipment manufacturing, the construction of electricity generating stations as well as transportation and distribution networks, and the work on the rebuilding and the reduction of damage in the electricity distribution network, in the fields of engineering, operation and customer services, according to SANA agency
There was a talk about a new agreement between the two sides, when Kharboutli announced that an Iranian company would visit Syria to sign a contract for the rehabilitation of the Aleppo power station, explaining that the financial scheduling which was included in the contract with the company would cost about $ 93 million, as reported by the pro-regime newspaper al-Watan, in October.
This is Iran’s second contract regarding the Aleppo station, as the first was signed with the RPRC Corporation, affiliated to the Ministry of Electricity, for the rehabilitation of the plant with a working capacity of 1065 MW.
Source » enabbaladi